Problem 17-13

Here is a list of activity times for a project as well as crashing costs for its activities. Determine which activities should be crashed and the total cost of crashing if the goal is to shorten the project by three weeks as cheaply as possible. (Omit the “$” sign in your response.)

 

Activity Duration (weeks) First Crash Second Crash
1-2 5 $8              $10             
2-4 6 7              9             
4-7 3 14              15             
1-3 3 9              11             
3-4 7 8              9             
1-5 5 10              15             
5-6 5 11              13             
6-7 5 12              14             

 

      Activity    Cost
  First crash    $    $    $ [removed]     
 
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code "Newclient" for a 15% Discount!

NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.